Cutover Dates

Date

Event/Process Responsible Party
Ongoing

Review pending overloads

  • If overload was paid, finish approvals
  • If overload was never paid, cancel overload

Review JEMS Rate and Title transactions

  • Cancel if not needed or moving forward before Workday go-live

Review current position vacancy announcements (PVLs) in JEMS PVL to determine

  • If PVL should be canceled
  • If PVL should be finalized
Dept/Division
June 12, 2025 Retro Transaction Deadline (transactions from 5C or before), must be entered by 4:30PM Dept/Division
June 14, 2025
  • Telecommuting agreements will freeze at 4:30PM
  • Update Personal Information will freeze at 4:30PM (Addresses, Contact Details, Emergency Contacts, Name, Marital Status, Ethnic Groups, Vet Status, Disability Status, etc)
Employee/Manager/Dept/Division
June 15-28, 2025
  • Last Pay Period in HRS-6B
  • Limited critical/essential HR transactions should be entered into HRS
  • Any transaction effective between 6/15 and 6/28 must be fully entered (HRS via JEMS) in advance by no later than 6/30 at 4:30PM
Dept/Division
June 16, 2025 Last day for 6A HR transaction entry into HRS, must be entered by 4:30PM Dept/Division
June 17, 2025 First snapshot of HRS data to be loaded into Workday ATP Team
June 19, 2025 Last day to Division Approve/Delegation Approve a PVL in JEMS Dept/Division
June 20, 2025 Last day to Division Approve/Delegation Approve a PVL Waiver in JEMS Dept/Division
June 25, 2025
  • Last Day to Division Approve a JEMS Rate and Title transaction effective through 6/28/2025
  • Last Day to submit and approve an overload in the overload system effective through 6/28/2025
Dept/Division
June 26, 2025 Retro Transaction Deadline (transactions from 6A or before), must be entered by 4:30PM Dept/Division
June 28, 2025
  • Latest effective date converted to Workday
  • Last day to update person assignment checklist (CBC and Position of Trust)
Dept/Division/ATP Team
June 29, 2025
  • First Pay Period in Workday begins (7A, 6/29-7/13)
  • Transactions effective 6/29/2025 and after will not convert to Workday even if they are entered into HRS in advance
Dept/Division
June 29-July 6, 2025
  • Freeze on new transaction entry
  • ATP Team will catch up on transactions effective 6/15-6/28
  • Some EIBs for transactions effective 6/29 will be loaded during this time (grad assistant increases)
ATP Team
June 30, 2025
  • Last day for 6B HR transaction entry into HRS, must be entered by 4:30PM​
  • HRS will become View Only at 4:30PM
Dept/Division/ATP Team
July 1, 2025
  • Second snapshot of HRS data and last payroll confirm in HRS (6B)
  • Last payroll confirm in HRS (6B)
ATP Team
July 7, 2025
  • Workday Opens for all Employees
  • Changes for the 7A must be manually entered if not loaded using an  EIB 
Dept/Division/ATP Team
July 17, 2025 First Payroll Run (7A) in Workday ATP Team

Questions? 